We are very excited to bring updates on the Nursing Center Renovation Project!
 
A & B WING UPDATE:
Exterior wall structures for the new dining rooms are being assembled, with roof work to follow. The target date for completion is mid May.
Beginning 3/18 – over the course of the next eight weeks, ceiling and wall work will begin.  Specific details have been discussed with residents, and letters mailed out to families.
 
G WING UPDATE:
Exterior structure work continues. Support structures and outside walls for the dining room expected very soon. A temporary wall has been built in the corridor to allow for demolition work of the existing dining room to proceed.
 
Please note: across the building, emergency exit locations and egress paths have changed. All areas are posted with the current exit procedures!